The Development Process

Great North Road Solar and Biodiversity Park has completed the Examination stage of the Development Consent Order process. The Examining Authority now has up to three months to prepare and submit its recommendation report to the Secretary of State, who then has a further period of up to three months to make the final decision. 

The Planning Process

Great North Road Solar and Biodiversity Park is classified as a Nationally Significant Infrastructure Project (NSIP) because it would generate more than 50 megawatts (MW) of electricity.   

The 2008 Planning Act defines the consent regime for an NSIP.  It requires that we apply for a Development Consent Order (DCO), which has been submitted to the Planning Inspectorate (PINS) rather than the local planning authority.  

PINS, acting on behalf of the Secretary of State for the Department of Energy Security and Net Zero (DESNZ), has now carefully examined our proposals and will make a recommendation to the Secretary of State on whether to grant consent for the development. Consent will be determined by the Secretary of State. 

Click here to learn more about the DCO process.

Stages of the NSIP Application Process

1) Pre-Application

2) Acceptance

3) Pre-Examination

4) Examination

5) Recommendation and Decision

6) Post Decision

Pre-application Consultation

Early and ongoing engagement is a cornerstone of our development process

Early and ongoing engagement is a cornerstone of our development process.

Community consultation forms an important part of the pre-application process for NSIPs. Ongoing engagement will influence and refine the design of GNR Solar and Biodiversity Park. Local councils, residents and community groups all have an important part to play. 

We held three phases of consultation, including:

  • The first non-statutory phase of consultation, which ran from 16 January 2024 to 27 February 2024. Here we invited feedback on our early-stage proposals for the Development. 

  • A second statutory phase of consultation, as required by the 2008 Planning Act. This ran from 09 January 2025 until 20 February 2025.

  • A targeted phase of consultation, which ran from 8 May to 6 June 2025. We carried out this targeted phase of consultation for after making some localised additions to the Preliminary Environmental Information Report (PEIR) Order Limits consulted on for Phase Two statutory consultation, which closed in February 2025.

Timeline

November
2023

Early
2024

Summer
2024

Early 2025

June
2025

2025 / 2026

Spring
2027

*Please note this timeline is indicative and may be subject to change