The Development Process

The Secretary of State granted development consent for Great North Road Solar and Biodiversity Park on 27 October 2026.

You can read the decision letter and Development Consent Order on our Documents page.

We are preparing the next stage of the project, including meeting the relevant requirements of the consent before construction can begin. We will publish the construction programme and further local engagement arrangements once confirmed.

The Planning Process

Great North Road Solar and Biodiversity Park is classified as a Nationally Significant Infrastructure Project (NSIP) because it would generate more than 100 megawatts (MW) of electricity.   

The 2008 Planning Act defines the consent regime for an NSIP.  It requires that we apply for a Development Consent Order (DCO), which has been submitted to the Planning Inspectorate (PINS) rather than the local planning authority.  

The application was examined by the Planning Inspectorate. Examination concluded on 28 April 2026, and the Examining Authority submitted its recommendation to the Secretary of State. Development consent was granted on 27 October 2026.

The project is now progressing through the relevant post-consent requirements.

Click here to learn more about the DCO process.

Stages of the NSIP Application Process

1) Pre-Application

2) Acceptance

3) Pre-Examination

4) Examination

5) Recommendation and Decision

6) Post Decision

Pre-application Consultation

Early and ongoing engagement is a cornerstone of our development process

Early and ongoing engagement is a cornerstone of our development process.

Pre-application consultation informed the design of the consented GNR Solar and Biodiversity Park. Feedback from local councils, residents and community groups helped shape the application. We will continue to engage with local communities as the project progresses through the relevant consent requirements and towards construction.

We held three phases of consultation, including:

  • The first non-statutory phase of consultation, which ran from 16 January 2024 to 27 February 2024. Here we invited feedback on our early-stage proposals for the Development. 

  • A second statutory phase of consultation, as required by the 2008 Planning Act. This ran from 9 January 2025 until 20 February 2025.

  • A targeted phase of consultation, which ran from 8 May to 6 June 2025. We carried out this targeted phase of consultation for after making some localised additions to the Preliminary Environmental Information Report (PEIR) Order Limits consulted on for Phase Two statutory consultation, which closed in February 2025.

Timeline

November
2023

Early
2024

Summer
2024

Early 2025

June
2025

2025 / 2026

Spring
2027

*Please note this timeline is indicative and may be subject to change